Goose Lake Dam - Boulder, Colorado |
|
Materials selected:
45 mil Reinforced Polypropylene
Quantity: 18,900 sq. ft.
Project:
Rehabilitate
the original Boulder Dam of the early 1900's for water storage fed
by snow melt from the Continental Divide.
Challenge:
This project involved the installation of a vertical membrane lining
system on the face of an existing rock and crib dam structure. The
highest section of the dam is 40' and varies in slope from 1:1 to
vertical.
The project site, located at over 10,000 ft. in elevation required construction to be completed late in season. Battling high winds and cold temperatures, the project was completed on-time and ready for the safe storage of the critical spring run-off.
Material: The original design called for a 60 mil HDPE liner over a 16 oz. geotextile underlayment fastened into an embed strip poured along the bottom footer of the dam face.
CLI proposed an alternative 45 mil RPP that could be fabricated into 5 panels and installed over the uneven facing provided.
Installation:
The geosynthetic design installed a 16 oz Non-woven
geotextile protective layer against the face of the dam
with a 45 mil Reinforced Polypropylene (RPP) geomembrane mechanically attached to the top and bottom of
the dam.
The advantage of RPP is the ability to pre-fabricate panels to size and limit the number of vertical field welds. This project was installed with only 4 field seams.