Dallas Eastside Water Treatment Plant Retention Lagoons - Sunnyvale, TX |
|
Materials selected:
28 oz Geotextile - 657,000 sq. ft.
40 mil Textured HDPE - 587,500 sq. ft.
12 oz Geoweb® - 572,000 sq. ft.
Problem:
Prior
to the installation of geosynthetics, the levee was plagued by
erosion.
Chronic problems caused by more than a dozen sliding failures per year on the outer slopes of the facility's water retention lagoons.
The lagoons, enclosed within a perimeter levee, were constructed with flexible membrane containment liners. The tops of the levees were capped with a paved access road.
Challenge:
To develop alternate means of resolving the sliding issues.
The exterior slopes, which had been constructed at a gradient of 3H: IV, were composed of highly expansive clay soils with PI (plasticity index) ranging from 21 to 75. Because of the expansive nature of the levee embankment soils, the slope surfaces suffered from severe shrinkage cracking during the dry summer months. Water entered these cracks during the rainy season and found pathways into the deeper soil layers, creating instability in the slope structure.
Installation:
With
the levee embankment already partially encapsulated by the lagoon
liner on the inside slope and the surface treatment on top, it was
decided to further encase the levee by placing a liner system and
surface erosion control on the outer slope. The
slopes were stripped of vegetative cover and graded in preparation
for the new slope protection system. An upper anchor trench was
excavated along the outside perimeter of the access road at the
top of the slope to anchor the various geosynthetic products
that formed the liner system and final slope cover.
The geocomposite liner system consisted of: a 40-mil textured HDPE lining, and a 28 oz. nonwoven geotextile,and would help maintain even moisture distribution within the levee embankment soils and protect the structure from the major changes in moisture content that were driving the volume change and cracking of the expansive clay soils. Based on the findings of the geotechnical engineers, it was agreed that sliding failures triggered by saturation of the deeper soil layers had to be stopped. The installation would also use an erosion resistant slope cover to protect the liner. The Presto Geoweb® cellular confinement system was specified with crushed granite gravel infill for the final slope cover. The geocellular system was well suited to this application as it restrained the sliding forces of the stone without requiring staking through the liner system. The perforated cells also enabled heavy water flows accumulating above the liner to quickly move down the covered slope without loss of the stone infill.
The large cell size enabled Colorado Lining International's installation team to work efficiently on the 3:1 slope face - running tendons - expanding, orienting and then securing the sections. An upper anchor trench was excavated along the outside perimeter of the access road at the top of the slope to anchor the various geosynthetic products that formed the liner system and final slope cover. The waterproof layer of textured HDPE lining was installed over the prepared sub grade followed by a 28-ounce nonwoven geotextile protection fabric.
With the composite liner system in place and tested, installation of the geocell layer began. A deadman anchor system–4 in. schedule 40 PVC pipe–was installed in the trench at the top of the slope and then the perforated geocell system sections were placed. Heavy-duty TP-91 tendons were run through the pre-drilled 4 in. cells and secured by wrapping and tying to the deadman anchor. The use of ATRA® restraint clips spread the working load of the gravel infill from the geocells to the tendons.
The final step involved filling the cells with crushed stone material to provide a final cover for the protected slope.
Upon delivery, a labor crew using long handled rakes spread the materials evenly in the cells.
The aggregate contractor, AAA Sand & Stone Inc., designed a conveyor system to efficiently deliver materials to the slope.
Conclusions:
This
composite slope protection installation gave the owner a long-term,
low maintenance
solution for a difficult problem. Combining
various geosynthetics: 40-mil
textured HDPE lining & 28
oz. nonwoven geotextile to
create a composite system can provide cost effective solutions
for complex erosion
control and
containment problems faced by civil and environmental engineers
The installation began in late August 2002 and was completed in early November. The successful installation and subsequent performance of our lining system, inspected each year since its completion in 1996, remains functioning as designed and intended, serving its community.