|
|
|
|
 |
| |
|
|
| |
|
Site
Considerations:
Whenever
possible, site selection should avoid areas where flooding or ground
water pressure can occur. The lining "bottom" should be
well above the water table. If the site selected is in an area where
organics are in the soil, or if gases can be generated by chemical
reaction, the design must allow for venting.
|
| |
|
|
| |
 |
|
| |
|
| Surface
Preparations: |
|
|
|
Surfaces
should be level and free of all sharp rocks (all rock and
stone greater than .05 diameter), objects, vegetation and
stubble. (Soil
sterilization may be necessary to kill roots and certain types
of grasses.)
The
subgrade surface should provide a unyielding foundation for
the geomembrane with no sharp or abrupt changes or break in
grade. Proper
compaction assures stability and support of the liner.
|
|
No
Yes
Rough
ground and standing water, mud, snow - any excessive moisture
- is counterproductive for liner deployment.
|
|
| |
 |
|
| |
|
| Controlling
Groundwater: |
|
|
|
Groundwater
should be taken into account and, if present, it will need
to be controlled both during and after construction. One method
for controlling groundwater is to develop a French drain system
under the lining that allows the water to flow laterally under
the lining without floating the lining.
|
|
A
good design for an underdrain is to pipe it to the outside
of the lake into a gravel sump. This allows the sump to run
continuously during construction and, with the placement of
an upright at this sump, the underdrain can be pumped if needed
to relieve hydrostatic pressure and gas buildup under the
lining system.
|
|
| |
 |
|
| |
|
| Slopes: |
|
|
|
Side slopes should be no steeper than 3:1 whenever feasible.
Contact CLI directly when site specifications or conditions
differ.
Slopes
are usually hand-raked to achieve proper smoothness.
|
|

|
|
| |
 |
|
| |
|
| Receipt
of Liner and Materials: |
|

The
pallets are shipped rolled with a tarp cover to prevent damage,
and to protect the tightly folded and rolled material from
direct sunlight and heat.
Each
pallet may weigh up to 5,000 lbs. and the rolls can be unloaded
and transported by field fork equipment of sufficient capacity.
|
|
Liner
panels are fabricated into large sheets to minimize field
seaming. These large panels are first accordian folded, then
rolled up on a core and strapped to a wooden pallet.
The
adhesives, solvents, shrouds and other items are generally
shipped with the panels. It is recommended that the liners
panels' protective covering not be removed until installation
and that any uncovered panels be stored out of direct sunlight.
|
|
|
| |
|
 |
|
| |
|
|
| Anchor
Trenches:
|
|
|
|
To
secure the edges of the lining in an earthen pit, an "anchor
trench" is dug. Anchor trenches are approx.
two foot wide by two foot deep (2' x 2') and
one foot back from the crest of the berm (standard trench
dimensions and depth vary according to project design.)
Dirt
removed should be raked out flat on the far side of the trench,
away from the pit, to be used to backfill after the liner
edges are laid out in the anchor trench, while allowing the
panels to be unrolled along the berm.
|
|

Slightly
rounding corners of the trench avoids sharp bends in the geomembrane.
The trench itself needs to be free of loose soil and rocks.
|
|
| |
|
 |
|
| |
|
|
| Site
Structures: |
|
|
|
Structures, piping, concrete, drains, and any associated work
should be completed prior to lining installation.
|
|
|
|
| |
|
 |
|
| |
|
|
| Liner
Deployment:
|
|

|
|
Use
a lift system that suspends a roll off the ground. The roll
is raised by a loader, forklift, crane or other lifting equipment
and then spooled off and deployed. An unwind stand can also
be used from a modified flatbed trailer.
|
|
|
| |
|
 |
|
| |
|
|
| Panel
Placement:
|
|

It
takes considerable manpower to deploy a liner. It is "pulled"
but not stretched. Minor wrinkles insure the liner is installed
in a relaxed condition.
A
ballast system, such as dead weights (sand bags) and anchor
trenches are used for all geomembranes installed in exposed
applications. For buried applications, the installed liner
should be temporarily secured by sand bags until cover soils
are placed, working from center to out.
|
|
Take
time when unloading and placing rolls of lining to avoid damage.
Verify the location of a panel or sheet before unrolling and
placement to avoid improper alignment.
Sandbags
(or similar ballast) are required to keep the panels in place
during installation, exposed or covered - a minimum of 25
bags per panel.
If
is it windy: wind uplift and wind suction forces can lift
exposed, unballasted liners off the ground and potentially
damage them.
Care
should be taken to avoid wrinkles in the seam areas and around
mechanical attachments.
|
|
|
| |
|
 |
|
| |
|
|
| Field
Seaming:
|
|
|
|
Pre-fabricating
panels at our facility into essentially larger panels
reduces the amount of field seaming a project requires. (Fabrication
seaming is performed under controlled conditions and the seams
are fully tested.)
The
lining material itself determines the types of field seaming
techniques used.
The
most commonly used process is solvent welding, which is very
similar to welding pipe and basically melts the adjacent panels
together. Wedge welding provides excellent seam properties
and reproducible welds and is faster and cleaner than solvents.
|
|

Now,
with advanced technology in field welding, the use of wedge
welders that apply heat and pressure to form a homogenous
weld are becoming the state-of-the-art.
|
|
| |
|
 |
|
| |
|
|
| Batten
Attachments:
|
|

Place
the geomembrane over the anchor bolt, place a strip of neoprene
gasket between the liner and batten strip an d secure the
batten strip with washers and nuts.
|
|
Liner
can be
attached to concrete structures. This attachment is acheived
using stainless steel batten.
The
stainless steel strips are attached to the concrete by inserting
stainless steel wedge-type anchor bolts into the concrete.
|
|
|
| |
|
 |
|
| |
|
|
| Pipe
Boots:
|
|
|
|
A
pipe boot is a "sleeve" that allows mechanical piping
to be placed as needed without destroying the integrity of
the liner.
An
undersized hole is cut in the center of the sleeve, stretched
over the pipe, creating a flange of material. Wrap pipe 12"
and tie into flange of material. Stainless stell clamp sleeve
to pipe.
Pipe
boots can be pre-made to your liner type and outer-diameter
pipe specifications. Shipped with the liner to your site,
this step reduces field installation time.
|
|

Panels
around piping penetrations are cut with rounded corners to
prevent tear propagation.
90-degree
and slope boots are also available.
|
|
| |
|
 |
|
| |
|
|
| Design
Notes: |
|
|
|
Driving
on the liner is permitted only with a 12" dirt covering.
No excessive speeds, no sharp turns.
|
|
Disclaimer:
These guidelines are for informational purposes only and are
intended as illustration or general information only and are
not intended as a guarantee or warranty. Colorado Lining International
assumes no responsibilities in connection with the use of
this information.
|
|